This is the third of a four part series on the history of Calgary’s ring road, covering the period when construction of the road first began. While this site continues to focus on the Southwest portion, I wanted to cover the history of the rest of the road, to provide some context to the story. Part one of this series (Initial Outlines) can be found here, and part two (Integrated Planning) can be found here.
After many studies, and many more years of planning, this period marked the first time that physical work on the project was undertaken, and the road was finally becoming a reality. Even with the route of the Transportation Utility Corridor (TUC) being largely set in the 1970s, the path to a finished road was never going to be straightforward. In this period there were (and still are) many issues to resolve, agreements to make, and studies to undertake. Despite the false-starts and the setbacks involved in the business of actually constructing a road, significant progress was made; the ring road went from being a line on a map to the beginnigs of a constructed freeway system that is currently close to being three-quarters finished. Continue reading “The Ring Road System – Implementation (1980 to 2001)”