SW Ring Road Elbow River Open House

The Weaselhead Glenmore Park Preservation Society is hosting a public open house to look at the Southwest Calgary Ring Road plans for the Weaselhead and Elbow river area. The open house, to be held on October 7th and moderated by former MLA Dave Taylor, will feature presentations by Alberta Transportation, Cows and Fish and the Miistakis Institute, as well as the Weaslehead/Glenmore Park Preservation Society itself.

The presentation by Alberta Transportation looks to be the only public presentation of the SW ring road plans before the Province begins their own ring road information sessions later this month.

SW Calgary Ring Road Open Forum Details
October 7, 2014
7:00 – 9:00 pm
Cedarbrae Community Centre, 11024 Oakfield Dr. S.W.

EDIT: October 21 2014
The presentation portion of the open house was filmed and can be viewed on the video below. It provides and excellent overview of the Elbow river crossing design and the challenges and decisions that led to the proposed solution, as well as an exploration of the environmental issues that surround the design and the crossing of the river valley:

 

Advertisement

Crossing the Elbow River – 1956 to 1986

The release of a ‘virtual tour’ video of the Southwest Calgary Ring Road this past week has given the public a chance to view the proposed plans for this road in a way that maps have not been able to. The detail and context provided by the video has raised concerns over the impacts the road will have on southwest Calgary, including the Elbow River, Fish Creek and the Weaselhead. The nature, size and proximity of the cut-and-fill river crossing, combined with a realignment of the rivers, appear to be at the heart of these concerns.

2014_elbow

(Source: Alberta Transportation)

The crossing of the Elbow river is arguably the most important link in the Southwest Calgary Ring Road project. This new crossing of the Elbow river in southwest Calgary, the first since the Glenmore causeway opened in 1963, is projected as being the single most utilized portion of the new road. Establishing this crossing has seen numerous proposals over the years; from a low-level bridge in the 1950s to a dam in the 1980s (creating a new reservoir upstream from the Weaselhead) to a consideration of a high-level bridge, and even talk of a tunnel, in the 2000s. A new crossing of the Elbow river is an idea that has undergone many revisions and alternatives in the decades since it was first proposed.

The first part of this story looks at the early proposals and the history of the crossing of the Elbow River, from the first proposal in 1956 to the project’s (temporary) cancellation in 1986. Part two, which looks at the modern river crossing plans and alternatives from 2000 to 2014, will follow.

Early plans: models and maps

In 1955 the Province of Alberta made public its desire to establish a bypass highway in Calgary’s southwest, and by the following year, the City had drafted initial plans for this road. Around the same time the City was also developing plans for the Glenmore Reservoir parks, and these two proposals would converge in the form of the first publicly released concept for the Southwest Ring Road, then known as the West Bypass, and its crossing of the Elbow river.

The ambitious plan for the proposed Glenmore Parks, containing an aquarium, a solarium, botanical gardens, an ‘Indian Village’ and more, was estimated to cost $3 million and would take upwards of 25 years to implement. When the City’s planning department was seeking approval from both the public and the City Council for the proposed park system surrounding the Glenmore Reservoir, they created a model of their proposed ideas. Along the western portion of the model lay the West Bypass, and its crossing of the Elbow river was presented to the public for the first time.

na-5600-8138a

(Glenbow Archives NA-5600-8138a. Click for an enlargement of the Elbow River crossing)

The crossing, depicted as a 4-lane low-level bridge of about 180m in length with some amount of cut-and-fill on the north bank of the valley, was only conceptual at this stage. Detailed work on the entire development had yet to be carried out at the time of the model’s creation, and no engineering had gone into the designs at this point. (The road is shown along the bottom of the photograph above). Continue reading “Crossing the Elbow River – 1956 to 1986”

West and Southwest Calgary Ring Road Virtual Tour

On August 25 2014 the Province of Alberta released 3D Virtual Tour renderings of the West and Southwest Calgary Ring Road projects.

Southwest Calgary Ring Road Project:

West Calgary Ring Road Project:

Click for more information on the 2013 Southwest Ring Road deal (plus updates in March 2014 and June 2014), and the History of the Southwest Ring Road. For more information on the history of the West Calgary Ring Road, Click Here.

Ring Road Update June 2014

The Provincial Government today released the functional design plans for the West and Southwest Calgary Ring Road project. Starting at the Bow river crossing of Stoney trail NW and heading south to Macleod trail at Highway 22x via the Tsuut’ina reserve, this last section of the ring road measures 31km, contains 66 bridges, 20 interchanges and several crossings of the Bow river, the Elbow river and the Fish creek. A full breakdown of the details can be found here, or at the Alberta Transportation website here.

W&SW_Ring_Road

Though the new release contains little new information on the physical road itself, one of the major changes announced involves the staging of construction. While the Province and the Tsuut’ina Nation are still awaiting the Federal Government to approve the land transfer that was agreed upon last year, the Province has stated that rather than build the West leg first, as was previously announced, the Southwest leg of the road would be the first to start construction. The timelines are currently unchanged from earlier estimates, and it is hoped by the Province to have a contractor awarded and construction begun in 2016.

Other key points:

• 80,000-100,000 cars are projected to use certain sections of the road.

• Data from the 2013 flood is being used to evaluate the bridge designs, to ensure they will “accommodate future flooding events of a similar magnitude”.

• A P3 financing model is still being evaluated, and a decision will be made upon the completion of a business case advocating for or against such a model.

• 2 million cubic metres of rock and 5 million cubic metres of dirt will be moved to create a path for the road up the Paskapoo Slopes, beside Canada Olympic Park.

• According to the most recent available plans from 2008, The Elbow river valley at the Weaselhead will be filled from the current width of about 1000 metres wide down to 90 metres wide, with the remaining gap to be bridged. The fill height and road will range from between 5 to 15 metres (16 to 50 feet) above the current valley floor.

• An environmental assessment by the Province is reportedly underway, either in addition to, or as a continuation of, the environmental assessment begun in 2006.

• Public information sessions are planned for the fall or early winter of 2014.

Maps of the West Calgary Ring Road (from North to South)

Highway 1 (Trans Canada Highway), Valley Ridge blvd NW, and the twinning of the existing Stoney Trail bridge over the Bow river:

11_WCRR_TCH_VRidge_small

Continue reading “Ring Road Update June 2014”

Ring Road Update March 2014

The recent release of the 2014 Provincial Budget brought with it some new details regarding the funding of the Southwest Calgary Ring Road. In addition, the Province has released some initial timing and staging details regarding the implementation of the road, including the possible division of the road into two separate construction projects.

ringroad_march_2014

The Budget and the $5 Billion Price Tag

Released on March 6, the 2014 Alberta Budget sets aside $2.698 billion towards both Calgary and Edmonton’s ring road projects over the next three years. Of this, Finance Minister Doug Horner noted that $1.8 billion is to be dedicated to the Southwest Calgary Ring Road. In an address on March 7 to the Calgary Chamber of Commerce, Minister Horner reportedly stated that the full construction of the remaining portion of Calgary’s ring road would cost around $5 billion. The decision to deliver the project via traditional delivery or through Public Private Partnerships has yet to be made, and the Province is currently “investigating the viability of delivering the final segment of Calgary’s ring road in two separate projects using the Public Private Partnership (P3) procurement process” Continue reading “Ring Road Update March 2014”

From No to Maybe: The turning point for the SW Ring Road, part 1

The approval of a ring road agreement between the Tsuut’ina and the Province of Alberta in October of 2013 has opened the door for the long-planned Southwest Calgary Ring Road to be built through what is currently the Tsuut’ina Nation reserve. By any measure, the vote to accept the deal was overwhelmingly in favour, but the idea of selling reserve land for the freeway has not always been a popular one amongst Nation members.

With a deal now agreed to locate the ring road through the reserve, a once formidable divide between the idea of retaining reserve land and selling it has seemingly been bridged, but what changed? Why has that idea of selling the land, once thoroughly rejected by Tsuut’ina members and leadership, now been embraced?

Ring Road Planning

Although Calgary had planned for a ring road from as early as the mid-1950s, the early designs would have seen limited, or at times non-existent, incursions into the Tsuut’ina reserve. Early designs were proposed to be largely located within Calgary’s city limits, and while there have been sporadic discussions between the City and the Nation regarding the acquisition of land for a road, in the early days these talks would appear to be perfunctory.

It wasn’t until the 1970s that more considered thought was given to planning the Southwest Calgary Ring Road through the Tsuut’ina reserve in a substantial way.

1975_ROUTE_F Continue reading “From No to Maybe: The turning point for the SW Ring Road, part 1”

Road Purchases and Surrenders

The October 2013 ring road agreement between the Province of Alberta and the Tsuut’ina Nation has recently been heralded by the Province and the media as a historic agreement between these two parties. While the scale, compensation and long-term impacts of this deal are indeed unique, representing the largest ever land purchase from the Tsuut’ina reserve and the potential opening of the reserve for unprecedented development, it is not the first time a road corridor has been acquired by the Province through the reserve. The ring road agreement actually represents the seventh time that a Provincial road corridor has been secured through Tsuut’ina lands.

all_corridors_1900-20131. Priddis Trail, 1900
2. 37th Street SW, 1910
3. Priddis Trail Diversion, 1916
4. Highway 22/Bragg Creek Road, 1922
5. Balsam Avenue Bridge Approach, 1934
6. Highway 22 Widening, 1955
7. Southwest Calgary Ring Road, 2013

Continue reading “Road Purchases and Surrenders”

2013 Agreement and Design

The 2013 Ring Road Agreement between the Tsuut’ina Nation and the Province of Alberta was announced on Friday October 25 2013, marking the conclusion of the latest round of negotiations. A new deal, which was crucial in addressing concerns regarding the previous agreement from 2009, contains new compensation levels, new guarantees, and a slightly modified design for the road.

UPDATE JULY 2015: The Federal Government approved the addition to the Tsuut’ina reserve and the transfer of the road corridor to the Province in May 2015. Click here for all of the details.

The Nation will receive from the Province:

Guaranteed 5338.1 acres of crown land located to the west of the current reserve, which will be converted into reserve status, valued at $44,420,683.50 (See lands map below). The total land figure includes 5,018.1 acres of crown lands provided as compensation in the agreement (Shown in yellow in the map below), as well as an additional 320 acres of crown land that the Nation will purchase for $1,643,000 (Shown in blue in the map below).
• $275,000,000 in cash
• $65,643,900 additional funds to be used for the relocation and reconstruction costs for homes, businesses and roads currently located in the path of the road.

tsuutina_Land_Request_with_Consultation_Area_August16_2013.dgn

The Province will receive from the Nation:

1058 acres needed for the Transportation Utility Corridor (TUC) where the ring road would be built (shaded green in the map below)

In addition and apart from this agreement, the plan would see approximately 8 acres from the SW corner of the Weaselhead park purchased by the Province from the City of Calgary, while the existing high-pressure natural gas line and overhead transmission lines that run through the park would be removed from the natural area.

2013-09-05 Tsuu T'ina Final Agreement - Final

OTHER ASPECTS OF THE DEAL

In addition to the financial compensation and land transfers contained in the agreement, there are other clauses that dictate how the road would be implemented.

Continue reading “2013 Agreement and Design”

Unexploded Ordnance in Southwest Calgary

The 2013 southern Alberta floods did more to Calgary than damage houses and severely interrupt lives; the floods unearthed and highlighted a problem that has caused concern, and worse, for decades. In July, two unexploded military shells were found on the shores of the Elbow river in the Weaselhead area, exposing a legacy of unexploded ordnances (UXO) that lie just beneath the surface of a portion of southwest Calgary, including the potential route of the southwest ring road.

weaselhead_uxo

(Image of shell found in the Weaselhead area, July 2 2013. Courtesy Mark Langenbacher) Continue reading “Unexploded Ordnance in Southwest Calgary”

The Glenmore Land Claims

On June 6 2013 the Canadian government ratified a settlement agreement with the Tsuu T’ina Nation that was reached this past April regarding three specific land claims. These claims, known collectively as the Glenmore Reservoir land claims, were the result of actions taken in the 1930s regarding land in the Weaselhead area.

weaselhead_2

The $20.8 million settlement has now concluded claim negotiations that had been ongoing since 1996. With the potential for the largest ever sale of Tsuu T’ina land for the still under negotiations for the ring road, it is important to understand the context of historic land deals, and the problems and sensitivities that arose from them. Continue reading “The Glenmore Land Claims”