Storm Trunk Relocation: The first steps to the SW Ring Road

In June of 2015, the City of Calgary will begin to construct some of the first tangible work on the Southwest Calgary Ring Road Project. This work will not be on the road itself, but will be related to utilities that will run under part of the project.

The City and Province of Alberta has agreed to construct a new storm sewer line to replace the existing South Richmond Storm Trunk that currently crosses a portion of the Tsuut’ina Nation reserve known as ‘the 940‘. The new line will be located entirely within the City of Calgary city limits along 37th street SW in Lakeview when completed, while the old line will be abandoned. This abandonment and replacement is not due to the functionality or suitability of the existing infrastructure, rather it is necessary due to reasons that are political and jurisdictional in nature; reasons that go back more than 60 years.

stormtrunk_b

Continue reading “Storm Trunk Relocation: The first steps to the SW Ring Road”

Advertisement

SW Ring Road Information Sessions Announced

Alberta Transportation has announced the dates and locations for their upcoming information sessions, covering the West and Southwest Calgary Ring Road projects.

W&SW_Ring_Road Continue reading “SW Ring Road Information Sessions Announced”

SW Ring Road Elbow River Open House

The Weaselhead Glenmore Park Preservation Society is hosting a public open house to look at the Southwest Calgary Ring Road plans for the Weaselhead and Elbow river area. The open house, to be held on October 7th and moderated by former MLA Dave Taylor, will feature presentations by Alberta Transportation, Cows and Fish and the Miistakis Institute, as well as the Weaslehead/Glenmore Park Preservation Society itself.

The presentation by Alberta Transportation looks to be the only public presentation of the SW ring road plans before the Province begins their own ring road information sessions later this month.

SW Calgary Ring Road Open Forum Details
October 7, 2014
7:00 – 9:00 pm
Cedarbrae Community Centre, 11024 Oakfield Dr. S.W.

EDIT: October 21 2014
The presentation portion of the open house was filmed and can be viewed on the video below. It provides and excellent overview of the Elbow river crossing design and the challenges and decisions that led to the proposed solution, as well as an exploration of the environmental issues that surround the design and the crossing of the river valley:

 

West and Southwest Calgary Ring Road Virtual Tour

On August 25 2014 the Province of Alberta released 3D Virtual Tour renderings of the West and Southwest Calgary Ring Road projects.

Southwest Calgary Ring Road Project:

West Calgary Ring Road Project:

Click for more information on the 2013 Southwest Ring Road deal (plus updates in March 2014 and June 2014), and the History of the Southwest Ring Road. For more information on the history of the West Calgary Ring Road, Click Here.

Ring Road Update June 2014

The Provincial Government today released the functional design plans for the West and Southwest Calgary Ring Road project. Starting at the Bow river crossing of Stoney trail NW and heading south to Macleod trail at Highway 22x via the Tsuut’ina reserve, this last section of the ring road measures 31km, contains 66 bridges, 20 interchanges and several crossings of the Bow river, the Elbow river and the Fish creek. A full breakdown of the details can be found here, or at the Alberta Transportation website here.

W&SW_Ring_Road

Though the new release contains little new information on the physical road itself, one of the major changes announced involves the staging of construction. While the Province and the Tsuut’ina Nation are still awaiting the Federal Government to approve the land transfer that was agreed upon last year, the Province has stated that rather than build the West leg first, as was previously announced, the Southwest leg of the road would be the first to start construction. The timelines are currently unchanged from earlier estimates, and it is hoped by the Province to have a contractor awarded and construction begun in 2016.

Other key points:

• 80,000-100,000 cars are projected to use certain sections of the road.

• Data from the 2013 flood is being used to evaluate the bridge designs, to ensure they will “accommodate future flooding events of a similar magnitude”.

• A P3 financing model is still being evaluated, and a decision will be made upon the completion of a business case advocating for or against such a model.

• 2 million cubic metres of rock and 5 million cubic metres of dirt will be moved to create a path for the road up the Paskapoo Slopes, beside Canada Olympic Park.

• According to the most recent available plans from 2008, The Elbow river valley at the Weaselhead will be filled from the current width of about 1000 metres wide down to 90 metres wide, with the remaining gap to be bridged. The fill height and road will range from between 5 to 15 metres (16 to 50 feet) above the current valley floor.

• An environmental assessment by the Province is reportedly underway, either in addition to, or as a continuation of, the environmental assessment begun in 2006.

• Public information sessions are planned for the fall or early winter of 2014.

Maps of the West Calgary Ring Road (from North to South)

Highway 1 (Trans Canada Highway), Valley Ridge blvd NW, and the twinning of the existing Stoney Trail bridge over the Bow river:

11_WCRR_TCH_VRidge_small

Continue reading “Ring Road Update June 2014”

90th Avenue and the Southwest Ring Road

First appearing on plans together nearly 60 years ago, and shown as connected in every major road plan since, 90th avenue SW and the Southwest Calgary Ring Road have a long and inseparable history. The connection of these two roads together, initially planned out of convenience, and later out of necessity, continues to play a significant role in the history of the ring road. Calls to keep 90th avenue from being connected to the ring road have been heard in recent years, and it is important to understand the history of this road, and why the connection of 90th avenue is seen as an indispensable part of the ring road plan.

The Origins of 90th Avenue SW

1953_90th

90th avenue is an arterial road in Calgary’s southwest, south of the Glenmore Reservoir, that has existed in some form or another since the early days of the City. Early settlers in the region traveled its path to access their land, and by the early 20th century, a dirt road had been created which served a small number of homesteads in the area. This arrangement, pictured above in 1953, went largely unchanged for many years. When the foreseeable encroachment of an expanding City of Calgary finally necessitated it, bigger plans for the road were initiated.

Forward Planning and a Growing City

In the early to mid 1950s the City had begun to more fully embrace a civic planning program; one that was more forward looking than had been undertaken in decades. The City was creating plans for areas that were then rural, but would one day be developed as part of a rapidly-growing City. The earliest modern plan for 90th avenue can be traced back to 1953 when the City created it’s earliest internal Ring Road plan. 90th avenue SW between Macleod Trail and 37th street SW was at that time an integral part of the Ring Road, and formed the southern portion of the City’s first complete Southwest Calgary Ring Road route.

1953-highlight

(Source: Untitled Map. December 1953. City of Calgary Corporate Records, Archives. Board of Commissioners S. IV box 189 F. 39.)

This configuration did not last long, and soon the main Ring Road route continued south, beyond 90th avenue SW. By 1956 a masterplan for the development of parks around the Glenmore Reservoir was developed by the City (shown below), and included a modified 90th avenue SW proposal. These plans mark the first time that plans for the Southwest Calgary Ring Road and 90th avenue SW were shown to the public.

Glennore_1956Then called ‘South Glenmore Drive’, 90th avenue was depicted much as we know it today, running from 14th street SW to 37th street SW, where it connected directly to the ring road. This basic layout was retained in Calgary’s first approved transportation plan, 1959’s Calgary Metropolitan Transportation Plan (shown below as 92nd avenue).

1959_90th Continue reading “90th Avenue and the Southwest Ring Road”

From No to Maybe: The turning point for the SW Ring Road, part 2

This article follows on from the previous article, From No to Maybe: The turning point for the SW Ring Road, part 1.

—–

By the close of the 1970s, the Tsuut’ina Nation and the City of Calgary seemed to be at an impasse regarding the Southwest Calgary Ring Road (or the Sarcee Trail Extension, as it was then known). Though generally indicating resistance to the idea of allowing a road through the reserve, the Nation nonetheless had been willing to continue to engage with the City in discussions, noting that any chance of success hinged on the Nation deriving certain benefits from the road. The City meanwhile had seemingly made it clear that they were not prepared to entertain certain requests of the Nation, particularly access from the ring road to potential developments on the reserve, and the extension of City utilities to those developments.

1984_reserve_view

At the same time, and in a seemingly contradictory move, the City had begun to limit itself from building the road along a route through the Weaselhead area within the City limits, thus ensuring that it needed to acquire land from the Nation in order to build the road. Though conditions to this point had not yet been right for progress, both parties seemed to be heading towards a middle ground, and information and cooperation were the last hurdles to clear before the story of the ring road could move forward. Continue reading “From No to Maybe: The turning point for the SW Ring Road, part 2”

Ring Road Update March 2014

The recent release of the 2014 Provincial Budget brought with it some new details regarding the funding of the Southwest Calgary Ring Road. In addition, the Province has released some initial timing and staging details regarding the implementation of the road, including the possible division of the road into two separate construction projects.

ringroad_march_2014

The Budget and the $5 Billion Price Tag

Released on March 6, the 2014 Alberta Budget sets aside $2.698 billion towards both Calgary and Edmonton’s ring road projects over the next three years. Of this, Finance Minister Doug Horner noted that $1.8 billion is to be dedicated to the Southwest Calgary Ring Road. In an address on March 7 to the Calgary Chamber of Commerce, Minister Horner reportedly stated that the full construction of the remaining portion of Calgary’s ring road would cost around $5 billion. The decision to deliver the project via traditional delivery or through Public Private Partnerships has yet to be made, and the Province is currently “investigating the viability of delivering the final segment of Calgary’s ring road in two separate projects using the Public Private Partnership (P3) procurement process” Continue reading “Ring Road Update March 2014”

The West Calgary Ring Road

Though the route of the southwest ring road through the Tsuut’ina reserve has in recent years garnered the most attention of the unfinished portions of Calgary’s bypass network, there are actually two additional pieces of infrastructure needed to complete the ring. Aside from the south leg, which extends the road to Macleod Trail in the south, there is also the West Calgary Ring Road, defined as the portion of the road that connects the Trans Canada Highway to Highway 8. This is the piece that I will cover here.

Early West Side Planning

1956-2009_west_ring_road

The earliest complete plans for a ring road around Calgary, dating from 1956, plotted much of the western leg of the circuit along the 53rd street SW corridor, better known today as Sarcee Trail. While the route to the north and south of this leg would undergo revisions, this western portion would remain largely unchanged for nearly 30 years, and the road would continue to be planned along the Sarcee Trail corridor until the mid 1980s. Continue reading “The West Calgary Ring Road”

A Brief History of the Southeast Calgary Ring Road

The opening of the southeast Calgary ring road in November marked not only the completion of over three years of construction, but also of the fulfillment of a goal first set out by the Province of Alberta nearly 60 years earlier.

1955-2013_SE(A progression of bypass proposals for East Calgary is shown above)

Early Bypasses

In the 1950s, when bypass plans were first considered for the Calgary area, the city’s main arterial roads radiated from the core, and the primary bridges over the City’s rivers were largely located downtown. To access the industrial southeast, residents living in the new suburbs of the northwest and southwest would have to drive through or near the increasingly congested core. In order to allow drivers not bound for downtown to bypass central Calgary, and in order to allow long-range travelers to connect between major highways without adding to the congestion of the city, several bypass roads would be proposed that would avoid the city centre. These early bypass plans would include such a facility along the city’s southeastern edge.

Continue reading “A Brief History of the Southeast Calgary Ring Road”